Bottlenecks stay on B.C. Road-Addahole in DK; public have robust time driving by means of battered stretches stuffed with potholes
Vehicles plying on the battered stretch between B.C. Road and Addahole in Dakshina Kannada district on the Mangaluru-Bengaluru NH-75. | Photo Credit: ANIL KUMAR SASTRY
The incomplete stretches the place the NHAI couldn’t present even a single carriageway embody Periyashanthi, Bajathur, Mogru, and Perne, and the general public are pressured to make use of these stretches which might be battered and stuffed with potholes.
The NHAI has now stated that the steadiness stretches that contain large rock blasting, rock-cutting and hill-cutting, could be accomplished by January 2026.
Gopalakrishna Pai from Mani stated, “The widening work was nonetheless occurring close to Periyashanthi (Dharmasthala Cross) underneath Package 2 of the freeway widening challenge (Periyashanthi-Addahole, 14 km). About 400-metre stretch of the freeway was in a pathetic situation, with concern of tyres getting caught.”
The work has come to a standstill in Nellyadi city, a distance of about one km, with a pending court docket case of individuals demanding an elevated street as a substitute of the already erected vehicular overpasses.
The NHAI has now stated that the steadiness stretches that contain large rock blasting, rock-cutting and hill-cutting, could be accomplished by January 2026. | Photo Credit: ANIL KUMAR SASTRY
A couple of parts of the freeway remained incomplete on the Kanchana-Mata stretch and at Mogru close to Uppinangady abutting Netravathi river, he stated. A portion of the freeway between Uppinangady and Perne, the place an enormous hill-cutting was nonetheless on, doesn’t have no less than one accomplished carriageway, Mr. Pai stated.
Going by the tempo of labor, it appeared that the challenge, so far as carriageways are involved, would possibly get accomplished by December, and the complete work, together with service roads, would go on until October 2026, he stated.
No path board
Both carriageways of vehicular overpasses at Panemangaluru, Melkar, and the two.1 km-long Kalladka Flyover at the moment are open for visitors, whilst one carriageway of the vehicular overpass at Mani and Uppinangady are open, with work nonetheless ongoing on the opposite carriageway, stated Madhava Mathapathi from Mangaluru.
While automobiles sure to Bengaluru take the Mani junction vehicular overpass after descending the Kalladka Flyover, these driving in direction of Puttur get confused to maneuver on the service street to the left simply earlier than the vehicular overpass to take diversion in direction of proper on the Mani Junction, Mr. Mathapathi stated.
The NHAI ought to have supplied a path board earlier than the vehicular overpass, he added.
Published – July 27, 2025 08:33 pm IST